Ghost Schedules... are you at risk?

Although seldom brought into the limelight for reasons other than legal action, Ghost Schedules are not an uncommon occurrence in the Construction Industry. A recent study by the Navigant Construction Forum decided to take a deeper look into the creation and use of Ghost Schedules, as well as the reasoning to why they are created to begin with.

What is a Ghost Schedule?
Ghost Schedules have been used behind the scenes on capital construction projects for many years and for various purposes. To put it simply, a Ghost Schedule is a schedule other than the current project schedule. It is typically created and kept by one of the contract parties (such as an owner or contractor) when they believe the current one to be unreliable. A contractor's Ghost Schedule is not a substitute to the baseline schedule. Inversely, an owner's Ghost Schedule is not a tool for comparing against the project schedule in progress meetings.

Why are they created?
Ghost schedules are created for any number of reasons. A contractor may create one to road map a planned early completion even when an owner refuses to approve the contractor's early completion schedule. An owner may have one to interpret the project status without input from the contractor, which they will then use in the background for decisions such as granting requested time extensions. These parties could then use their Ghost Schedules to analyze and determine the potential impact of design changes and decision making before bringing them into actual discussion, or push for suppliers and subcontractors to meet early start and finish dates in order to beat the project schedule date.

Who you gonna call?
Ghost Schedules are a product of perceived necessity; they are created when a group believes the current schedule to be inept. Implementing a solution that streamlines the schedule so that all parties are satisfied diminishes the desire to create ghost schedules in the first place. That's where Projectmates comes in. Our construction program management software takes project scheduling to a new level of efficiency and transparency by acting as a single platform of seamless communication between all parties. The software trivializes the time it takes to make schedule revisions, immediately notifies team members of updates on major milestones, and is constantly visible to the entire team 24/7. Our wealth of reports and scheduling features allow owners to easily analyze project status. On top of schedule tracking, Projectmates provides document management, cost controls, and communication tools that further help owners and contractors complete projects on time and even early. With Projectmates, consider this ghost busted!

Related Articles

projectmates-short-video-thumbnail

Construction Project Management Made Easy

Harnessing the power of real time information for capital projects to facilitate communication  In a recent study by Mckinsey Global Institute, it showed that three major asset classes make up the..

Read more

A Better Way to Manage Capital Construction in 2017

We all know that software should be easy to use and intuitive, but the majority of solutions available today come with a steep learning curve and a glossary of new definitions to learn. The goal for..

Read more

Projectmates
Blog Sign Up

Enjoy what you're reading? Subscribe to receive the latest news in construction management.

Featured Post

Don't Miss the Latest: Whats New in Projectmates 18.0

Don't Miss the Latest: Whats New in Projectmates 18.0

If you missed last week's webinar on Projectmates new version release, don't worry, here is a recap of all the exciting new features that the Projectmates team has worked hard to incorporate!

Read more

Latest Tweets